DURATION: 2021 - Ongoing

Gove Pond 5

CLIENT: McCosker Contracting

About this Project

The Gove Pond 5 project involves the capping of the pond as part of the Gove operations closure.  The multiyear project includes construction of extensive drainage systems, pond lining and three capping layers all built to tight tolerances. 

Insight Survey’s involvement includes:

  • Survey Management
  • Implementation and Management of Machine Guidance
  • EOM reporting and Mass Haul development
  • Earthworks set out and as constructed reporting
  • UAV Surveys

Project Info

Date: