DURATION: 2018 - Ongoing

Yarwun RMA

CLIENT: McCosker Contracting

About this Project

Raising of all 5 Red Mud Dam tailings dam walls over the consecutive years of 2018 to 2023, associated filter blankets and chimneys placement of subsoil drainage network, depressurisation trenches, internal road networks, and borrow pit creation and rehabilitation.

Insight Survey have provided the following services:

  • Survey Management
  • Implementation and Management of Machine Guidance
  • EOM reporting and Mass Haul development
  • Earthworks set out and as constructed reporting
  • UAV Surveys
  • Laser Scanning Survey

Project Info

Date: